Bil
|
Perkara
|
Jadual
|
Sebenar
|
Status
|
1.
|
Inception Report
|
24/05/12
|
24/05/12
|
Ditolak
|
Rev. A
|
|
03//07/12
|
Terima dengan ulasan
|
2.
|
Draft Preliminary Scheme Report
|
28/06/12
|
06/07/12
|
Terima dengan ulasan
|
3.
|
Preliminary Scheme Report (PSR)
|
02/08/12
|
02/08/12
|
Ditolak
|
Rev. A
|
|
11/10/12
|
Terima dengan ulasan
|
Rev. B
|
|
14/03/13
|
Sedang disemak
|
4.
|
Draft Engineering Feasibility and Cost Report (DEFCR)
|
30/08/12
|
11/09/12
|
Terima dengan ulasan
|
5.
|
Preliminary Engineering Feasibility and Cost Report (PEFCR)
|
04/10/12
|
05/10/12
|
Ditolak
|
Rev. A
|
|
07/02/13
|
Telah disemak
|
6.
|
Draft Final Report
|
18/10/12
|
18/10/12
|
Terima dengan ulasan
|
7.
|
Final Report
|
01/11/12
|
01/11/12
|
Ditolak
|
Rev. A
|
|
16/01/13
|
Telah disemak
|
|
|
|
|
|
Kemaskini Terakhir (Monday , 19 AUG 2013)